Velociraptor Solar II — Project Summary

Queue ID
ERCOT-28INR0322
Capacity
251.73 MW
Technology
Solar
Status
active
Location
Ector, Texas
Region
ERCOT
Developer
Greyhound Solar 3 LLC
IA Status

Velociraptor Solar II

BetaActiveSolar - Photovoltaic SolarERCOTLive · ERCOT

251.73 MW generation in Ector, Texas · In queue since May 2025 · Proposed COD November 2028

251.73 MW

Capacity

0

Components

10 months

In Queue

IA Status

COD target: 2028

Interconnection Timeline

Total Duration

3y 6m

Pre-Study0%
Queue EntryMay 27, 2025

Interconnection request submitted to ISO/RTO

Interconnection Study

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-11-17

Project Details

State

Texas

County

Ector

Region

ERCOT

Developer

Greyhound Solar 3 LLC

Utility

Entity

ERCOT

Point of Interconnection

Tap south bus Odessa EHV SW (11028) - Wolf Switch (11010) 345KV section at (31.740371, -102.502076)

Data Source

Live · ERCOT

No news available for this project.