Champion Road BESS
BetaActiveOther - Battery Energy StorageERCOTLive · ERCOT
205.2 MW storage in Angelina, Texas · In queue since February 2025 · Proposed COD September 2028
205.2 MW
Capacity
0
Components
1y 1m
In Queue
—
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
3y 7m
Pre-Study0%
Queue EntryFeb 14, 2025
Interconnection request submitted to ISO/RTO
Interconnection Study
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2028-09-30
Project Details
State
Texas
County
Angelina
Region
ERCOT
Developer
Horizon Energy Storage Greenfield Project Holdings LLC
Utility
—
Entity
ERCOT
Point of Interconnection
138 kV Tap 3328 Lufkin South - 3324 Lufkin Switch Tap East
Data Source
Live · ERCOT