Magnet Solar
ERCOT-28INR0297BetaActiveSolarPhotovoltaic SolarERCOTLive · ERCOT
503.09 MW generation in Borden, TX · In queue since April 2025 · Proposed COD October 2028
503.09 MW
Capacity
0
Components
1 year
In Queue
—
IA Status
Signed Dec 2025
Interconnection Timeline
Queue → IA
8 months
IA → COD
2y 10m
Total Duration
8 months
Construction0%
Queue EntryApr 21, 2025
Interconnection request submitted to ISO/RTO
Interconnection Study
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection AgreementDec 11, 2025
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 12–24 months
Commercial Operation
Proposed COD: 2028-10-06
Project Details
State
TX
County
Borden
Region
ERCOT
Developer
HyFuels Big Spring Solar LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Faraday Substation 345kV - Bus #59905
Data Source
Live · ERCOT
No news available for this project.