Wildflower Storage
BetaActiveOther - Battery Energy StorageERCOTLive · ERCOT
359.1 MW storage in Navarro, Texas · In queue since June 2025 · Proposed COD September 2028
359.1 MW
Capacity
0
Components
9 months
In Queue
—
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
3y 3m
Pre-Study0%
Queue EntryJun 5, 2025
Interconnection request submitted to ISO/RTO
Interconnection Study
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2028-09-30
Project Details
State
Texas
County
Navarro
Region
ERCOT
Developer
Wildflower Storage LLC
Utility
—
Entity
ERCOT
Point of Interconnection
Drane Switch 345 kV substation on Venus Switch (1906) - Navarro (68091) 345 kV line
Data Source
Live · ERCOT
No news available for this project.