Outrider BESS
302 MW storage in Dickens, Texas · In queue since June 2025 · Proposed COD September 2028
302 MW
Capacity
0
Components
9 months
In Queue
—
IA Status
COD target: 2028
Total Duration
3y 3m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-09-30
State
Texas
County
Dickens
Region
ERCOT
Developer
Sanders Hollow Energy Center, LLC
Utility
—
Entity
ERCOT
Point of Interconnection
Tap 345 kV 59904 Cottonwood (W_CW_345) - 60500 Edith Clarke (EDITHCLA7A) CKT. Approximately distance from the POI to Cottonwood Substation is 11.13 miles and to Edith Clarke Substation 77.6 miles.