Wood Fern Wind
BetaActiveWind - Wind TurbineERCOTLive · ERCOT
197.3 MW generation in Van Zandt, Texas · In queue since January 2025 · Proposed COD June 2029
197.3 MW
Capacity
0
Components
1y 2m
In Queue
—
IA Status
COD target: 2029
Interconnection Timeline
Total Duration
4y 5m
Pre-Study0%
Queue EntryJan 31, 2025
Interconnection request submitted to ISO/RTO
Interconnection Study
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2029-06-07
Project Details
State
Texas
County
Van Zandt
Region
ERCOT
Developer
Wood Fern Wind LLC
Utility
—
Entity
ERCOT
Point of Interconnection
Tap 345kV #2432 Tri-Corner to #3102 Tyler Grande
Data Source
Live · ERCOT
No news available for this project.