Miracle Ranch Solar SLF
BetaActiveSolar - Photovoltaic SolarERCOTLive · ERCOT
221.6 MW generation in Webb, Texas · In queue since February 2025 · Proposed COD June 2028
221.6 MW
Capacity
0
Components
1y 1m
In Queue
—
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
3y 4m
Pre-Study0%
Queue EntryFeb 25, 2025
Interconnection request submitted to ISO/RTO
Interconnection Study
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2028-06-30
Project Details
State
Texas
County
Webb
Region
ERCOT
Developer
Miracle Ranch LLC
Utility
—
Entity
ERCOT
Point of Interconnection
138kV North Laredo (8909_NLARSW4A) to Barrera (8717_BARRERA4A) - AEP
Data Source
Live · ERCOT
No news available for this project.