Soluce Cotton Solar — Project Summary

Queue ID
ERCOT-28INR0267
Capacity
202.91 MW
Technology
Solar
Status
active
Location
Cottle, Texas
Region
ERCOT
Developer
CTPB1, LLC
IA Status

Soluce Cotton Solar

BetaActiveSolar - Photovoltaic SolarERCOTLive · ERCOT

202.91 MW generation in Cottle, Texas · In queue since February 2025 · Proposed COD July 2028

202.91 MW

Capacity

0

Components

1y 1m

In Queue

IA Status

COD target: 2028

Interconnection Timeline

Total Duration

3y 5m

Pre-Study0%
Queue EntryFeb 14, 2025

Interconnection request submitted to ISO/RTO

Interconnection Study

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-07-29

Project Details

State

Texas

County

Cottle

Region

ERCOT

Developer

CTPB1, LLC

Utility

Entity

ERCOT

Point of Interconnection

Tap 345kV 59904 COTTONWOOD - 60500 EDITH CLARKE

Data Source

Live · ERCOT