Agricola BESS
BetaActiveOther - Battery Energy StorageERCOTLive · ERCOT
— storage in Austin, Texas · In queue since March 2025 · Proposed COD May 2029
—
Capacity
0
Components
1 year
In Queue
—
IA Status
COD target: 2029
Interconnection Timeline
Total Duration
4y 2m
Pre-Study0%
Queue EntryMar 24, 2025
Interconnection request submitted to ISO/RTO
Interconnection Study
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2029-05-31
Project Details
State
Texas
County
Austin
Region
ERCOT
Developer
Agricola BESS LLC
Utility
—
Entity
ERCOT
Point of Interconnection
Tap 138kV GEBHARDT (#44700) - Wallis (#44740)
Data Source
Live · ERCOT
No news available for this project.