Hittson Creek Solar
BetaActiveSolarERCOTLBNL + Live
404 MW generation in Callahan, TX · In queue since December 2024 · Proposed COD December 2028
404 MW
Capacity
1
Components
Solar
1y 3m
In Queue
Facility Study
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
4 years
Facilities Study50%
Queue EntryDec 19, 2024
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2028-12-15
Project Details
State
TX
County
Callahan
Region
ERCOT
Developer
174 Power Global Properties
Utility
—
Entity
ERCOT
Point of Interconnection
Tapping the two 345 kV Lines: Sam Line Reactor (Bus# 68005) - Reata (Bus# 68051) and Latimer (Bus# 68008) - Reata (Bus# 68051).
Data Source
LBNL + Live
No news available for this project.