Dahlia Solar
BetaActiveSolar - Photovoltaic SolarERCOTLive · ERCOT
200.98 MW generation in La Salle, Texas · In queue since February 2025 · Proposed COD July 2028
200.98 MW
Capacity
0
Components
1y 1m
In Queue
—
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
3y 5m
Pre-Study0%
Queue EntryFeb 14, 2025
Interconnection request submitted to ISO/RTO
Interconnection Study
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2028-07-02
Project Details
State
Texas
County
La Salle
Region
ERCOT
Developer
Dahlia Energy LLC
Utility
—
Entity
ERCOT
Point of Interconnection
Tap 138kV 5723 Los Angeles - 5705 Fowlerton
Data Source
Live · ERCOT