Allthorn Solar
BetaActiveSolar - Photovoltaic SolarERCOTLive · ERCOT
231.5 MW generation in Duval, Texas · In queue since February 2025 · Proposed COD January 2029
231.5 MW
Capacity
0
Components
1y 1m
In Queue
—
IA Status
COD target: 2029
Interconnection Timeline
Total Duration
3y 11m
Pre-Study0%
Queue EntryFeb 14, 2025
Interconnection request submitted to ISO/RTO
Interconnection Study
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2029-01-15
Project Details
State
Texas
County
Duval
Region
ERCOT
Developer
ALLTHORN SOLAR, LLC
Utility
—
Entity
ERCOT
Point of Interconnection
Tap 138 kV BRUNI4A (#8297) - CRESTONI4A (#8695)
Data Source
Live · ERCOT
No news available for this project.