GPlains Solar
BetaActiveSolar - Photovoltaic SolarERCOTLive · ERCOT
151.29 MW generation in Ector, Texas · In queue since April 2025 · Proposed COD June 2029
151.29 MW
Capacity
0
Components
11 months
In Queue
—
IA Status
COD target: 2029
Interconnection Timeline
Total Duration
4y 2m
Pre-Study0%
Queue EntryApr 21, 2025
Interconnection request submitted to ISO/RTO
Interconnection Study
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2029-06-21
Project Details
State
Texas
County
Ector
Region
ERCOT
Developer
Gypsum Plains Solar, LLC
Utility
—
Entity
ERCOT
Point of Interconnection
Tap 138kV #1013 WOLFSS_8 - #1103 SANDHLTA_8
Data Source
Live · ERCOT
No news available for this project.