Rio Star Energy Storage
BetaActiveOther - Battery Energy StorageERCOTLive · ERCOT
143.6 MW storage in Wichita, Texas · In queue since February 2025 · Proposed COD April 2029
143.6 MW
Capacity
0
Components
1y 1m
In Queue
—
IA Status
COD target: 2029
Interconnection Timeline
Total Duration
4y 2m
Pre-Study0%
Queue EntryFeb 14, 2025
Interconnection request submitted to ISO/RTO
Interconnection Study
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2029-04-20
Project Details
State
Texas
County
Wichita
Region
ERCOT
Developer
Rio Star Energy Storage, LLC
Utility
—
Entity
ERCOT
Point of Interconnection
Tap 1464 Wichita Falls South Switch – 1474 Scotland 138 kV
Data Source
Live · ERCOT
No news available for this project.