Gypsum Plains Storage
BetaActiveOther - Battery Energy StorageERCOTLive · ERCOT
211.14 MW storage in Ector, Texas · In queue since January 2025 · Proposed COD June 2029
211.14 MW
Capacity
0
Components
1y 2m
In Queue
—
IA Status
COD target: 2029
Interconnection Timeline
Total Duration
4y 5m
Pre-Study0%
Queue EntryJan 31, 2025
Interconnection request submitted to ISO/RTO
Interconnection Study
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2029-06-21
Project Details
State
Texas
County
Ector
Region
ERCOT
Developer
Gypsum Plains Solar, LLC
Utility
—
Entity
ERCOT
Point of Interconnection
Tap 345kv 11010 Wolf - 18544 Reiter
Data Source
Live · ERCOT
No news available for this project.