Complex Serenity Wind
971 MW generation in Armstrong, Texas · In queue since June 2025 · Proposed COD April 2029
971 MW
Capacity
0
Components
9 months
In Queue
—
IA Status
COD target: 2029
Total Duration
3y 10m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-04-16
State
Texas
County
Armstrong
Region
ERCOT
Developer
Serenity Wind, LLC
Utility
—
Entity
ERCOT
Point of Interconnection
Double tap 345 kV Alibates (bus# 23900) to Tule Canyon (bus# 23914) and the Alibates (bus# 23900) to Midpoint Switch (bus# 23931)
Data Source
Live · ERCOT
Brazilian company SERENA propels Texas' wind energy growth with billion-dollar investment in Armstrong County
Wind power is the second largest source of energy in Brazil. As of this past summer the country has around 7000 wind turbines.
Brazilian company SERENA propels Texas' wind energy growth with billion-dollar investment in Armstrong County
Wind power is the second largest source of energy in Brazil. As of this past summer the country has around 7000 wind turbines.