Badger Solar
BetaActiveSolar - Photovoltaic SolarERCOTLive · ERCOT
301.83 MW generation in Upton, Texas · In queue since February 2025 · Proposed COD May 2029
301.83 MW
Capacity
0
Components
1y 1m
In Queue
—
IA Status
COD target: 2029
Interconnection Timeline
Total Duration
4y 3m
Pre-Study0%
Queue EntryFeb 12, 2025
Interconnection request submitted to ISO/RTO
Interconnection Study
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2029-05-25
Project Details
State
Texas
County
Upton
Region
ERCOT
Developer
174 Power Global Properties, LLC
Utility
—
Entity
ERCOT
Point of Interconnection
345 kV North McCamey Substation (Bus# 76000)
Data Source
Live · ERCOT
No news available for this project.