Fluvanna Max BESS
50 MW storage in Scurry, TX · In queue since December 2024 · Proposed COD September 2029
50 MW
Capacity
1
Components
Battery
1y 3m
In Queue
Facility Study
IA Status
COD target: 2029
Total Duration
4y 9m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-09-14
State
TX
County
Scurry
Region
ERCOT
Developer
Fluvanna Max Solar LLC
Utility
—
Entity
ERCOT
Point of Interconnection
11305-DERMOTT-345 kV A 345kV gen-tie line, approximately 5.5 miles long, will connect the Fluvanna Max BESS (Co-located with 29INR0077) project to the Dermott Substation (Scurry County), terminating at an assigned bay within the Dermott Substation.
Data Source
LBNL + Live