Sunburst Solar
BetaActiveSolarERCOTLBNL + Live
301.6 MW generation in San Patricio, TX · In queue since October 2024 · Proposed COD March 2029
301.6 MW
Capacity
1
Components
Solar
1y 5m
In Queue
Facility Study
IA Status
COD target: 2029
Interconnection Timeline
Total Duration
4y 5m
Facilities Study50%
Queue EntryOct 10, 2024
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2029-03-16
Project Details
State
TX
County
San Patricio
Region
ERCOT
Developer
Indigo Solar, LLC
Utility
—
Entity
ERCOT
Point of Interconnection
Tap LONHILL (Bus#8455) to KATOEN (Bus#8579).
Data Source
LBNL + Live