Sisters Solar II
BetaActiveSolarERCOTLBNL + Live
205.54 MW generation in Ector, TX · In queue since October 2024 · Proposed COD December 2028
205.54 MW
Capacity
1
Components
Solar
1y 5m
In Queue
Facility Study
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
4y 2m
Facilities Study50%
Queue EntryOct 21, 2024
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2028-12-15
Project Details
State
TX
County
Ector
Region
ERCOT
Developer
Oberon Solar III, LLC
Utility
—
Entity
ERCOT
Point of Interconnection
tap 345kV 11010 Wolf Switching Station - 10012 Meteor
Data Source
LBNL + Live