Gail Mountain Solar
ERCOT-28INR0176BetaActiveSolarERCOTLBNL + Live
244.4 MW generation in Borden, TX · In queue since October 2024 · Proposed COD August 2028
244.4 MW
Capacity
1
Components
Solar
1y 6m
In Queue
Facility Study
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
3y 10m
Facilities Study50%
Queue EntryOct 29, 2024
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2028-08-25
Project Details
State
TX
County
Borden
Region
ERCOT
Developer
Gail Mountain Solar, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 345kV 59905 Faraday - 59900 Long Draw
Data Source
LBNL + Live
No news available for this project.