Gail Mountain Solar — Project Summary

Queue ID
ERCOT-28INR0176
Capacity
244.4 MW
Technology
Solar
Status
active
Location
Borden, TX
Region
ERCOT
Developer
Gail Mountain Solar, LLC
IA Status
Facility Study

Gail Mountain Solar

ERCOT-28INR0176BetaActiveSolarERCOTLBNL + Live

244.4 MW generation in Borden, TX · In queue since October 2024 · Proposed COD August 2028

244.4 MW

Capacity

1

Components

Solar

1y 6m

In Queue

Facility Study

IA Status

COD target: 2028

Interconnection Timeline

Total Duration

3y 10m

Facilities Study50%
Queue EntryOct 29, 2024

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-08-25

Project Details

State

TX

County

Borden

Region

ERCOT

Developer

Gail Mountain Solar, LLC

Utility

Entity

ERCOT

Service Type

Point of Interconnection

Tap 345kV 59905 Faraday - 59900 Long Draw

Data Source

LBNL + Live

No news available for this project.