Guajillo Wind
BetaActiveWindERCOTLBNL + Live
204 MW generation in Duval, TX · In queue since December 2024 · Proposed COD September 2028
204 MW
Capacity
1
Components
Wind
1y 3m
In Queue
Facility Study
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
3y 9m
Facilities Study50%
Queue EntryDec 19, 2024
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2028-09-01
Project Details
State
TX
County
Duval
Region
ERCOT
Developer
Guajillo Wind LLC
Utility
—
Entity
ERCOT
Point of Interconnection
Tap 345 kV 80079 Cruce - 5901 San Miguel
Data Source
LBNL + Live