Brookesmith Storage
BetaActiveOther - Battery Energy StorageERCOTLive · ERCOT
351 MW storage in Brown, Texas · In queue since April 2025 · Proposed COD May 2029
351 MW
Capacity
0
Components
11 months
In Queue
—
IA Status
COD target: 2029
Interconnection Timeline
Total Duration
4y 1m
Pre-Study0%
Queue EntryApr 1, 2025
Interconnection request submitted to ISO/RTO
Interconnection Study
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2029-05-07
Project Details
State
Texas
County
Brown
Region
ERCOT
Developer
Brookesmith Storage LLC
Utility
—
Entity
ERCOT
Point of Interconnection
Tap Brown Switch #1444 – Russell Gap Switch #3348
Data Source
Live · ERCOT
No news available for this project.