Coke BESS — Project Summary

Queue ID
ERCOT-28INR0155
Capacity
220.3 MW
Technology
Battery
Status
active
Location
Coke, TX
Region
ERCOT
Developer
Coke ESS, LLC
IA Status
Facility Study

Coke BESS

BetaActiveBatteryERCOTLBNL + Live

220.3 MW storage in Coke, TX · In queue since October 2024 · Proposed COD April 2028

220.3 MW

Capacity

1

Components

Battery

1y 5m

In Queue

Facility Study

IA Status

COD target: 2028

Interconnection Timeline

Total Duration

3y 6m

Facilities Study50%
Queue EntryOct 1, 2024

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-04-10

Project Details

State

TX

County

Coke

Region

ERCOT

Developer

Coke ESS, LLC

Utility

Entity

ERCOT

Point of Interconnection

76090 Divide Switchyard 345kV

Data Source

LBNL + Live

No news available for this project.