Salt-Lick Storage — Project Summary

Queue ID
ERCOT-28INR0134
Capacity
155.3 MW
Technology
Battery
Status
active
Location
Culberson, TX
Region
ERCOT
Developer
Salt-Lick Storage, LLC
IA Status
Facility Study

Salt-Lick Storage

BetaActiveBatteryERCOTLBNL + Live

155.3 MW storage in Culberson, TX · In queue since October 2024 · Proposed COD June 2028

155.3 MW

Capacity

1

Components

Battery

1y 5m

In Queue

Facility Study

IA Status

COD target: 2028

Interconnection Timeline

Total Duration

3y 8m

Facilities Study50%
Queue EntryOct 10, 2024

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-06-01

Project Details

State

TX

County

Culberson

Region

ERCOT

Developer

Salt-Lick Storage, LLC

Utility

Entity

ERCOT

Point of Interconnection

11198 Elcor_8 138 KV

Data Source

LBNL + Live

No news available for this project.