River Boat Solar
BetaActiveSolarERCOTLBNL + Live
502.2 MW generation in Mitchell, TX · In queue since September 2024 · Proposed COD September 2028
502.2 MW
Capacity
1
Components
Solar
1y 6m
In Queue
Facility Study
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
4 years
Facilities Study50%
Queue EntrySep 4, 2024
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2028-09-25
Project Details
State
TX
County
Mitchell
Region
ERCOT
Developer
Champion Creek Solar, LLC
Utility
—
Entity
ERCOT
Point of Interconnection
Tap 345 kV Bus # 10053 Cattlemen 5 - Bus #76030 Gasconades Creek
Data Source
LBNL + Live
No news available for this project.