Half Moon Solar
ERCOT-28INR0127BetaActiveSolarPhotovoltaic SolarERCOTLive · ERCOT
512.5 MW generation in Starr, TX · In queue since January 2025 · Proposed COD July 2029
512.5 MW
Capacity
0
Components
1y 3m
In Queue
—
IA Status
Signed Sep 2025
Interconnection Timeline
Queue → IA
8 months
IA → COD
3y 10m
Total Duration
8 months
Construction0%
Queue EntryJan 13, 2025
Interconnection request submitted to ISO/RTO
Interconnection Study
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection AgreementSep 8, 2025
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 12–24 months
Commercial Operation
Proposed COD: 2029-07-01
Project Details
State
TX
County
Starr
Region
ERCOT
Developer
NextEra Energy Interconnection Holdings, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
#80231 Pronto 345kV
Data Source
Live · ERCOT
No news available for this project.