Silverbell Solar
BetaActiveSolarERCOTLBNL + Live
125.63 MW generation in Red River, TX · In queue since August 2024 · Proposed COD September 2028
125.63 MW
Capacity
1
Components
Solar
1y 7m
In Queue
Facility Study
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
4y 1m
Facilities Study50%
Queue EntryAug 16, 2024
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2028-09-30
Project Details
State
TX
County
Red River
Region
ERCOT
Developer
Silverbell Energy Center, LLC
Utility
—
Entity
ERCOT
Point of Interconnection
Tap 138kV Rivercrest SES 1780 - Deport REA 1768
Data Source
LBNL + Live