Silverbell Solar — Project Summary

Queue ID
ERCOT-28INR0125
Capacity
125.63 MW
Technology
Solar
Status
active
Location
Red River, TX
Region
ERCOT
Developer
Silverbell Energy Center, LLC
IA Status
Facility Study

Silverbell Solar

BetaActiveSolarERCOTLBNL + Live

125.63 MW generation in Red River, TX · In queue since August 2024 · Proposed COD September 2028

125.63 MW

Capacity

1

Components

Solar

1y 7m

In Queue

Facility Study

IA Status

COD target: 2028

Interconnection Timeline

Total Duration

4y 1m

Facilities Study50%
Queue EntryAug 16, 2024

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-09-30

Project Details

State

TX

County

Red River

Region

ERCOT

Developer

Silverbell Energy Center, LLC

Utility

Entity

ERCOT

Point of Interconnection

Tap 138kV Rivercrest SES 1780 - Deport REA 1768

Data Source

LBNL + Live

No news available for this project.