Axis Ridge Wind
750.05 MW generation in Sutton, TX · In queue since November 2024 · Proposed COD March 2030
750.05 MW
Capacity
1
Components
Wind
1y 4m
In Queue
Facility Study
IA Status
COD target: 2030
Total Duration
5y 4m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2030-03-19
State
TX
County
Sutton
Region
ERCOT
Developer
Axis Ridge Wind, LLC
Utility
—
Entity
ERCOT
Point of Interconnection
Tap 345kV 60709 Oersted - 60616 Edison
Data Source
LBNL + Live
Project Finance Brief: Doral Renewables Secures $1.5 Billion for Solar Project
Doral Renewables, a utility-scale renewable energy project developer, secured $1.5 billion in construction project financing for the Mammoth South, Mammoth...
How to harvest plentiful low-level winds on existing wind farms
Wind farm owners need cost-effective vertical axis wind turbines (VAWTs) that operate efficiently in high turbulence and that do so without wake.
How to harvest plentiful low-level winds on existing wind farms
Wind farm owners need cost-effective vertical axis wind turbines (VAWTs) that operate efficiently in high turbulence and that do so without wake.
Wind Farm Turbulence Statewide
The winds of change are blowing across Alabama as renewable energy projects are proposed in Cherokee, Etowah and Baldwin counties.
Last updated 2026-03-26