Vast Sands Power I (TEF -Due Diligence) — Project Summary

Queue ID
ERCOT-28INR0105
Capacity
440 MW
Technology
Gas
Status
active
Location
Ward, TX
Region
ERCOT
Developer
Permian Power I LLC
IA Status
Facility Study

Vast Sands Power I (TEF -Due Diligence)

ERCOT-28INR0105BetaActiveGasERCOTLBNL + Live

440 MW generation in Ward, TX · In queue since July 2024 · Proposed COD May 2028

440 MW

Capacity

1

Components

Gas

1y 9m

In Queue

Facility Study

IA Status

COD target: 2028

Interconnection Timeline

Total Duration

3y 10m

Facilities Study50%
Queue EntryJul 22, 2024

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-05-01

Project Details

State

TX

County

Ward

Region

ERCOT

Developer

Permian Power I LLC

Utility

Entity

ERCOT

Service Type

Point of Interconnection

Tap 345kV 11010 Wolf Switch - 11188 Quarry Field Switch Ckt 2

Data Source

LBNL + Live