Catamount Storage
BetaActiveBatteryERCOTLBNL
515.44 MW storage in Harris, TX · In queue since September 2024 · Proposed COD June 2028
515.44 MW
Capacity
1
Components
Battery
1y 6m
In Queue
Facility Study
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
3y 9m
Facilities Study50%
Queue EntrySep 4, 2024
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2028-06-01
Project Details
State
TX
County
Harris
Region
ERCOT
Developer
TOCE TX BESS 3, LLC
Utility
—
Entity
ERCOT
Point of Interconnection
Tap 345kV 46100 North Belt - 40850 Jordan CKT 99
Data Source
LBNL
No news available for this project.