Pham BESS
BetaActiveBatteryERCOTLBNL + Live
132.78 MW storage in Anderson, TX · In queue since June 2024 · Proposed COD April 2028
132.78 MW
Capacity
1
Components
Battery
1y 9m
In Queue
Facility Study
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
3y 10m
Facilities Study50%
Queue EntryJun 13, 2024
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2028-04-17
Project Details
State
TX
County
Anderson
Region
ERCOT
Developer
ASB1, LLC
Utility
—
Entity
ERCOT
Point of Interconnection
Tap 138kV 3281 TENNCLNY_8 - 3284 BETO_8
Data Source
LBNL + Live
No news available for this project.