EmberYork (TEF - Due Diligence)
ERCOT-28INR0089BetaActiveGasERCOTLBNL + Live
900 MW generation in Austin, TX · Proposed COD January 2028
900 MW
Capacity
1
Components
Gas
—
In Queue
Facility Study
IA Status
COD target: 2028
Interconnection Timeline
Facilities Study50%
Queue Entry
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2028-01-01
Project Details
State
TX
County
Austin
Region
ERCOT
Developer
EmberYork Energy Center
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
TAP 138kV WALLIS 44740 - GERBHRT 44700
Data Source
LBNL + Live
News & Articles (1)Beta
Last updated 2026-03-14