West Royal Natural Gas
BetaActiveGasERCOTLBNL + Live
888 MW generation in Upton, TX · In queue since June 2024 · Proposed COD June 2030
888 MW
Capacity
1
Components
Gas
1y 9m
In Queue
Facility Study
IA Status
COD target: 2030
Interconnection Timeline
Total Duration
6 years
Facilities Study50%
Queue EntryJun 13, 2024
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2030-06-01
Project Details
State
TX
County
Upton
Region
ERCOT
Developer
Invenergy Energy Transition Development LLC
Utility
—
Entity
ERCOT
Point of Interconnection
76000 L_NORTMC5_1Y 345kV
Data Source
LBNL + Live