Turtle Rock Storage
BetaActiveBatteryERCOTLBNL + Live
135.59 MW storage in Freestone, TX · In queue since May 2024 · Proposed COD July 2028
135.59 MW
Capacity
1
Components
Battery
1y 10m
In Queue
Facility Study
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
4y 2m
Facilities Study50%
Queue EntryMay 9, 2024
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2028-07-02
Project Details
State
TX
County
Freestone
Region
ERCOT
Developer
Turtle Rock Energy Center, LLC
Utility
—
Entity
ERCOT
Point of Interconnection
Tap 138 kV 13501 Clayhill to 13681 Reed
Data Source
LBNL + Live