Turtle Rock Storage — Project Summary

Queue ID
ERCOT-28INR0080
Capacity
135.59 MW
Technology
Battery
Status
active
Location
Freestone, TX
Region
ERCOT
Developer
Turtle Rock Energy Center, LLC
IA Status
Facility Study

Turtle Rock Storage

BetaActiveBatteryERCOTLBNL + Live

135.59 MW storage in Freestone, TX · In queue since May 2024 · Proposed COD July 2028

135.59 MW

Capacity

1

Components

Battery

1y 10m

In Queue

Facility Study

IA Status

COD target: 2028

Interconnection Timeline

Total Duration

4y 2m

Facilities Study50%
Queue EntryMay 9, 2024

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-07-02

Project Details

State

TX

County

Freestone

Region

ERCOT

Developer

Turtle Rock Energy Center, LLC

Utility

Entity

ERCOT

Point of Interconnection

Tap 138 kV 13501 Clayhill to 13681 Reed

Data Source

LBNL + Live

No news available for this project.