Daystar Solar — Project Summary

Queue ID
ERCOT-28INR0073
Capacity
150 MW
Technology
Solar
Status
active
Location
Karnes, TX
Region
ERCOT
Developer
Choate Solar, LLC
IA Status
Facility Study

Daystar Solar

BetaActiveSolarERCOTLBNL + Live

150 MW generation in Karnes, TX · In queue since April 2024 · Proposed COD March 2028

150 MW

Capacity

1

Components

Solar

1y 11m

In Queue

Facility Study

IA Status

COD target: 2028

Interconnection Timeline

Total Duration

3y 11m

Facilities Study50%
Queue EntryApr 15, 2024

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-03-15

Project Details

State

TX

County

Karnes

Region

ERCOT

Developer

Choate Solar, LLC

Utility

Entity

ERCOT

Point of Interconnection

5728 Choate 138kV

Data Source

LBNL + Live

No news available for this project.