Mirando Valley Wind
ERCOT-28INR0072BetaActiveWindERCOTLBNL + Live
351 MW generation in Jim Hogg, TX · In queue since August 2024 · Proposed COD July 2028
351 MW
Capacity
1
Components
Wind
1y 8m
In Queue
Facility Study
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
3y 11m
Facilities Study50%
Queue EntryAug 16, 2024
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2028-07-06
Project Details
State
TX
County
Jim Hogg
Region
ERCOT
Developer
ACE DevCo NC LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 345kV 80220 Cenizo - 80079 Cruce Ckt-1
Data Source
LBNL + Live
No news available for this project.