Bullring Wind 1
ERCOT-28INR0037BetaActiveWindERCOTLBNL + Live
303.5 MW generation in Starr, TX · In queue since May 2024 · Proposed COD June 2028
303.5 MW
Capacity
1
Components
Wind
1y 11m
In Queue
Facility Study
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
4y 1m
Facilities Study50%
Queue EntryMay 9, 2024
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2028-06-30
Project Details
State
TX
County
Starr
Region
ERCOT
Developer
ACE DevCo NC LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 345 kV 80355 DelSol7A - 80079 Cruce Ckt 1
Data Source
LBNL + Live
No news available for this project.