Brela BESS LLC — Project Summary

Queue ID
ERCOT-28INR0030
Capacity
251.3 MW
Technology
Battery
Status
active
Location
Wharton, TX
Region
ERCOT
Developer
Brela BESS LLC
IA Status
Facility Study

Brela BESS LLC

BetaActiveBatteryERCOTLBNL + Live

251.3 MW storage in Wharton, TX · In queue since January 2024 · Proposed COD May 2028

251.3 MW

Capacity

1

Components

Battery

2y 2m

In Queue

Facility Study

IA Status

COD target: 2028

Interconnection Timeline

Total Duration

4y 4m

Facilities Study50%
Queue EntryJan 11, 2024

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-05-29

Project Details

State

TX

County

Wharton

Region

ERCOT

Developer

Brela BESS LLC

Utility

Entity

ERCOT

Point of Interconnection

44040 Bailey SW 345 kV

Data Source

LBNL + Live

No news available for this project.