Silverton Solar
BetaActiveSolarERCOTLBNL + Live
401.2 MW generation in Briscoe, TX · In queue since December 2023 · Proposed COD July 2029
401.2 MW
Capacity
1
Components
Solar
2y 3m
In Queue
Facility Study
IA Status
COD target: 2029
Interconnection Timeline
Total Duration
5y 7m
Facilities Study50%
Queue EntryDec 4, 2023
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2029-07-01
Project Details
State
TX
County
Briscoe
Region
ERCOT
Developer
NextEra Energy Interconnection Holdings, LLC
Utility
—
Entity
ERCOT
Point of Interconnection
Tap 345kV 23914 Tule Canyon - 79001 Cross_W1
Data Source
LBNL + Live