Silverton Solar — Project Summary

Queue ID
ERCOT-28INR0023
Capacity
401.2 MW
Technology
Solar
Status
active
Location
Briscoe, TX
Region
ERCOT
Developer
NextEra Energy Interconnection Holdings, LLC
IA Status
Facility Study

Silverton Solar

BetaActiveSolarERCOTLBNL + Live

401.2 MW generation in Briscoe, TX · In queue since December 2023 · Proposed COD July 2029

401.2 MW

Capacity

1

Components

Solar

2y 3m

In Queue

Facility Study

IA Status

COD target: 2029

Interconnection Timeline

Total Duration

5y 7m

Facilities Study50%
Queue EntryDec 4, 2023

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2029-07-01

Project Details

State

TX

County

Briscoe

Region

ERCOT

Developer

NextEra Energy Interconnection Holdings, LLC

Utility

Entity

ERCOT

Point of Interconnection

Tap 345kV 23914 Tule Canyon - 79001 Cross_W1

Data Source

LBNL + Live

No news available for this project.