Channing Wind — Project Summary

Queue ID
ERCOT-28INR0018
Capacity
352.38 MW
Technology
Wind
Status
active
Location
Oldham, TX
Region
ERCOT
Developer
NextEra Energy Interconnection Holdings, LLC
IA Status
Facility Study

Channing Wind

BetaActiveWindERCOTLBNL

352.38 MW generation in Oldham, TX · In queue since December 2023 · Proposed COD December 2028

352.38 MW

Capacity

1

Components

Wind

2y 3m

In Queue

Facility Study

IA Status

COD target: 2028

Interconnection Timeline

Total Duration

5 years

Facilities Study50%
Queue EntryDec 20, 2023

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-12-31

Project Details

State

TX

County

Oldham

Region

ERCOT

Developer

NextEra Energy Interconnection Holdings, LLC

Utility

Entity

ERCOT

Point of Interconnection

23906 AJ Swope Station 345kV

Data Source

LBNL

No news available for this project.