Varadero Solar
BetaActiveSolarERCOTLBNL + Live
304.74 MW generation in Limestone, TX · In queue since July 2023 · Proposed COD April 2029
304.74 MW
Capacity
1
Components
Solar
2y 8m
In Queue
Facility Study
IA Status
COD target: 2029
Interconnection Timeline
Total Duration
5y 9m
Facilities Study50%
Queue EntryJul 10, 2023
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2029-04-01
Project Details
State
TX
County
Limestone
Region
ERCOT
Developer
NextEra Energy Interconnection Holdings, LLC
Utility
—
Entity
ERCOT
Point of Interconnection
#68092 Liberty Station 345kV
Data Source
LBNL + Live
No news available for this project.