Oriole Solar
ERCOT-28INR0008BetaActiveSolarERCOTLBNL + Live
503.91 MW generation in Knox, TX · In queue since May 2023 · Proposed COD December 2028
503.91 MW
Capacity
1
Components
Solar
2y 11m
In Queue
Facility Study
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
5y 7m
Facilities Study50%
Queue EntryMay 15, 2023
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2028-12-29
Project Details
State
TX
County
Knox
Region
ERCOT
Developer
Rolling Plain Solar
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 345kV 6076 Foxtail - 60791 Perigee
Data Source
LBNL + Live
No news available for this project.