Tetris Solar
BetaActiveSolarERCOTLBNL + Live
350 MW generation in Zapata, TX · In queue since July 2023 · Proposed COD July 2029
350 MW
Capacity
1
Components
Solar
2y 8m
In Queue
Facility Study
IA Status
COD target: 2029
Interconnection Timeline
Total Duration
6 years
Facilities Study50%
Queue EntryJul 28, 2023
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2029-07-01
Project Details
State
TX
County
Zapata
Region
ERCOT
Developer
NextEra Energy Interconnection Holdings LLC
Utility
—
Entity
ERCOT
Point of Interconnection
TAP 345kV 80307 Del Sol 7C - 80225 Cenizo 7C