Pecan Ridge
BetaActiveOther - Battery Energy StorageERCOTLive · ERCOT
150.79 MW storage in McCulloch, Texas · In queue since December 2025 · Proposed COD June 2027
150.79 MW
Capacity
0
Components
3 months
In Queue
—
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
1y 6m
Pre-Study0%
Queue EntryDec 17, 2025
Interconnection request submitted to ISO/RTO
Interconnection Study
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2027-06-30
Project Details
State
Texas
County
McCulloch
Region
ERCOT
Developer
Luminous Energy Renewables LLC
Utility
—
Entity
ERCOT
Point of Interconnection
60386 HEARTLAN2A 69kV
Data Source
Live · ERCOT