Limitless Energy Hub I — Project Summary

Queue ID
ERCOT-27INR0581
Capacity
1238.25 MW
Technology
Gas
Status
active
Location
Wilbarger, TX
Region
ERCOT
Developer
Limitless Energy Hub I LLC
IA Status

Limitless Energy Hub I

ERCOT-27INR0581BetaActiveGasCombined-CycleERCOTLive · ERCOT

1,238.25 MW generation in Wilbarger, TX · In queue since November 2025 · Proposed COD December 2028

1,238.25 MW

Capacity

0

Components

5 months

In Queue

IA Status

Signed Dec 2025

Interconnection Timeline

Queue → IA

1 month

IA → COD

3 years

Total Duration

1 month

Construction0%
Queue EntryNov 5, 2025

Interconnection request submitted to ISO/RTO

Interconnection Study

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection AgreementDec 31, 2025

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 24–48 months

Commercial Operation

Proposed COD: 2028-12-01

Project Details

State

TX

County

Wilbarger

Region

ERCOT

Developer

Limitless Energy Hub I LLC

Utility

Entity

ERCOT

Service Type

Point of Interconnection

6101 RILEY7A Substation 345kV

Data Source

Live · ERCOT

No news available for this project.