Limitless Energy Hub I
ERCOT-27INR0581BetaActiveGasCombined-CycleERCOTLive · ERCOT
1,238.25 MW generation in Wilbarger, TX · In queue since November 2025 · Proposed COD December 2028
1,238.25 MW
Capacity
0
Components
5 months
In Queue
—
IA Status
Signed Dec 2025
Interconnection Timeline
Queue → IA
1 month
IA → COD
3 years
Total Duration
1 month
Construction0%
Queue EntryNov 5, 2025
Interconnection request submitted to ISO/RTO
Interconnection Study
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection AgreementDec 31, 2025
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 24–48 months
Commercial Operation
Proposed COD: 2028-12-01
Project Details
State
TX
County
Wilbarger
Region
ERCOT
Developer
Limitless Energy Hub I LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
6101 RILEY7A Substation 345kV
Data Source
Live · ERCOT