Paolo Sole Hamilton Solar
BetaActiveSolar - Photovoltaic SolarERCOTLive · ERCOT
40.63 MW generation in Hamilton, Texas · In queue since May 2025 · Proposed COD July 2028
40.63 MW
Capacity
0
Components
10 months
In Queue
—
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
3y 2m
Pre-Study0%
Queue EntryMay 27, 2025
Interconnection request submitted to ISO/RTO
Interconnection Study
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2028-07-11
Project Details
State
Texas
County
Hamilton
Region
ERCOT
Developer
Viridian Power Development, LLC
Utility
—
Entity
ERCOT
Point of Interconnection
#258 Hamilton 69 kV
Data Source
Live · ERCOT
No news available for this project.