Pecos Wind
BetaActiveWind - Wind TurbineERCOTLive · ERCOT
191 MW generation in Pecos, Texas · In queue since July 2025 · Proposed COD September 2027
191 MW
Capacity
0
Components
8 months
In Queue
—
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
2y 2m
Pre-Study0%
Queue EntryJul 7, 2025
Interconnection request submitted to ISO/RTO
Interconnection Study
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2027-09-30
Project Details
State
Texas
County
Pecos
Region
ERCOT
Developer
Midnight Energy Center, LLC
Utility
—
Entity
ERCOT
Point of Interconnection
Tap 345 kV 60404 Solstice (SOLSTICE7A) – 76002 Bakersfield (L_BAKERS5_1Y) CKT 2
Data Source
Live · ERCOT