Antila Solar
ERCOT-27INR0500BetaActiveSolarPhotovoltaic SolarERCOTLive · ERCOT
500 MW generation in Borden, TX · In queue since April 2025 · Proposed COD November 2027
500 MW
Capacity
0
Components
1 year
In Queue
—
IA Status
Signed Aug 2025
Interconnection Timeline
Queue → IA
4 months
IA → COD
2y 3m
Total Duration
4 months
Construction0%
Queue EntryApr 21, 2025
Interconnection request submitted to ISO/RTO
Interconnection Study
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection AgreementAug 13, 2025
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 12–24 months
Commercial Operation
Proposed COD: 2027-11-30
Project Details
State
TX
County
Borden
Region
ERCOT
Developer
Antila Solar LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
#59916 Buck Canyon 345kV
Data Source
Live · ERCOT