Draco Solar
BetaActiveSolar - Photovoltaic SolarERCOTLive · ERCOT
500 MW generation in Borden, Texas · In queue since April 2025 · Proposed COD August 2027
500 MW
Capacity
0
Components
11 months
In Queue
—
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
2y 4m
Pre-Study0%
Queue EntryApr 21, 2025
Interconnection request submitted to ISO/RTO
Interconnection Study
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2027-08-19
Project Details
State
Texas
County
Borden
Region
ERCOT
Developer
Draco Solar LLC
Utility
—
Entity
ERCOT
Point of Interconnection
Tap Long Draw (59900) – Faraday (59905) CKT 1 and LONGDRAW (59900) - GALVANI(59912) CKT 2
Data Source
Live · ERCOT